Traceability Report
The Traceability report follows the links from requirements through Test Cases and Test Case Executions to defects. For each requirement, it shows its Test Cases, their Test Case Executions, and the defects.

Create the Traceability report
- Go to Apps โบ Test Management โบ Reports. On the Create new report page, select Traceability report.
- In the Create new Traceability report window, select the Testing Project. A report covers one Testing Project.
- Optional: to narrow the requirements, enter a JQL query in Requirements scope.
- Click Generate report.
The report needs requirements defined in the Testing Project. For more on creating reports, see Reports.
Read the report
The report lists the requirements of the Testing Project. Next to each requirement are its Test Cases, their Test Case Executions, and the defects.
A requirement without Test Cases is highlighted in yellow.

Three tiles at the top summarize the report: Requirements, Assignees, and Defects. The Requirements tile shows the requirement coverage.
Adjust the view
- Turn on Show latest TCE to show only the latest Test Case Executions.
- Click Hide graphs to hide the graphs. Show graphs brings them back.
- Click Configure layout to change what the report shows.
Configure layout has two tabs.
- Work Item Layout: add up to 3 extra fields each for Requirements, Test Cases, and Defects.
- Testing Objects: choose which columns the report shows.


Export the report
Click Export and choose PDF or CSV.